Construction of Destination ONE is progressing smoothly, with Block 102 currently at 58.7% completion. The bottom section was recently lifted into place for joining, and the team is now focused on fabricating and assembling various components to meet specifications.
We are pushing to accelerate the preparation of hull outfitting. By the end of April, Block 102 will be turned for final welding and ready for outfitting and installation of components. This will allow us to complete as many hot work items as possible before moving to the sandblasting and paint sheds for the application of primer 161.
Block 103 is on the second jig and well underway with all deck plates and the first frame in place, currently at 33.3% completion. This marks an important milestone in the project's progress.
Overall, the total hull progress is at 17.99% completion, and the team is working diligently to ensure that the project stays on schedule. We are committed to maintaining the highest standards of quality and safety throughout the construction process. Regular monitoring of progress is being conducted, and updates will continue to be provided as the project advances.
We would like to acknowledge the hard work and dedication of our team in ensuring the smooth progress of the construction. Their commitment to excellence is evident in the quality of work being carried out.